Aldyl-A Replacement Program

Multiple locations throughout California

VPC Aldyl-A Pipeline Installation

VPC is actively replacing gas mains and service lines around California as part of an ongoing effort to upgrade plastic and steel pipelines with modern materials. Through 2020, crews have completed 63 projects ranging from $150K to $2M in size, installing 171,400 LF of main and replacing more than 3,250 services.

Business Line: Gas
Performed By: Veteran Pipeline Construction (VPC), a Charge company
Delivery Method: Construction services/Project management
Size: Approx. 30 miles of main and 3,200 services

Project Highlights

  • Completed 63 projects (through 2020)
  • Installed 171,400 linear feet of mainline
  • Replaced 3,253 services
  • Te-ins to existing gas lines

Project Services

  • Directional Drilling
  • Open Trench
  • Houseline Plumbing
  • Restoration
  • Pipe Splitting