Bonanza Rule 20A
Walnut Creek, California
This is the first VPC/VPI combined “cradle to grave” joint trench EPC project, which included design, civil construction, pulling cable, energizing, removal of electric conductors, installing new city-owned streetlight poles/facilities, and restoration. This Rule20A project in downtown Walnut Creek also included service connections at the panel and de-activating overhead service lines.
Business Line: | Gas and Electric |
---|---|
Performed By: | VPC/VPI |
Delivery Method: | Engineer, Procure, Construct (EPC) |
Size: | 1 mile |
Project Highlights
- 2”, 4” and 6” conduit via joint trench
- 4,479 linear feet of trenching
- Installing 16,579 feet of conduit for gas, electric, communications
- Five #7 vaults
- Four #5 vaults
- Installing 46 enclosures/concrete pads
- Pulling and terminating of cable
- Installation of 8 city streetlights
- Installation of 17 new gas services
Project Services
- Engineering
- Procurement
- Joint Trench Installation
- Excavation for streetlight foundations
- Panel Conversions
- Cable Pulling and Energization
- Traffic Control
- Hardscape restoration