High Speed Rail Selma
Selma to Earlimart, California
 
                        This project relocates overhead electrical lines underground in preparation for California High-Speed Rail Authority’s construction package 2-3, a 60-mile stretch within the counties of Fresno, Tulare and Kings. VPI installed conduit and vaults at various locations where the High-Speed Rail right away intersects existing infrastructure. Work included collaboration with multiple state and federal agencies, as well as other contractors performing work on the HSR project.
| Business Line: | Electric | 
|---|---|
| Performed By: | Veteran Power Infrastructure (VPI), a Charge company | 
| Delivery Method: | Construction services/Project management | 
| Size: | 6+ miles | 
Project Highlights
- 
35 locations crossing new HSR right away
- 
31,813 LF of trenching
- 
98 #7 vaults
- 
15 Auger bores
Project Services
- Utility Locating
- Directional Drilling
- Auger boring
- Traffic Control
- Vault Installation
- Engineering
- GPS as built data collection